| Phases |
Work packages |
Tasks |
| Phase1 |
WP1 – Identification of
barriers |
Task 1 – Analysis of
social and economic programmes and actions in the Sub-Saharan African
Countries |
| Appraisal
and analysis of current situation |
|
Task 2 – Identification
of barriers for CDM implementation in the Sub-Saharan African Countries |
| |
WP2 – Plan of Action to
overcome barriers |
Task 3 – Identification
of integrated actions and measures to overcome barriers in Sub-Saharan
African Countries |
| |
|
Task 4 – Formulation of a
Plan of Action to overcome barriers |
| Phase
2 |
WP4 – Identification of
ongoing and potential CDM projects |
Task 8 – Collection of
appropriate data and information |
| Methodology
for selection of CDM project |
|
Task 9 – Evaluation of
CDM eligibility of the selected ongoing projects |
|
WP3 –
Assessment of direct benefits and
co-benefits of potential CDM projects |
Task 5 – Formulation of
baselines and additionality analysis |
| |
|
Task 6 – Modelling
methodology to evaluate the direct benefits of CDM projects |
| |
|
Task 7 – Definition of a
matrix of co-benefits of CDM projects |
| Phase
3 |
WP5 – Development of a methodology
for mapping CDM potential |
Task 10 – Collection of
appropriate data fro CDM Mapping |
| Mapping
the CDM potential |
|
Task 11 – Construction of
appropriate scenaria |
|
|
Task 12 – Elaboration of
CDM potential Atlas |
| |
WP6 – Identification of
new potential CDM projects |
Task 13 – Project
selection |
| |
|
Task 14 – Selection of
three CDM projects |
| |
WP7 – Pre-feasibility
studies |
Task 15 – Pre-feasibility
study of three selected CDM projects |
| Phase
4 |
WP8
– Financial mechanism |
Task 16 – Development of
mechanisms for funding investment in clean technologies |
| Framework
for CDM implementation |
WP9 – Institutional and
infrastructural framework |
Task 17 – Elaboration of
appropriate framework for CDM implementation |
| Phase
5 |
WP10 – Dissemination of
the results |
Task 18 – Round Table of
Stakeholder Dialogues in Niger |
| Dissemination
of results and management of
the project |
|
Task 19 - Round Table of
Stakeholder Dialogues in Mozambique |
|
|
Task 20 – Elaboration of
dissemination materials |
| |
WP11 – Management of the
project |
Task 21 – Project
activity co-ordination |